Power Systems
Electrical Load Planning: Why It Comes Before Solar and Automation
Solar, backup power and smart automation all depend on the property's real electrical load. Here is how load planning works, with a worked example, and what it prevents.
Solar systems and smart automation are both sized around one number that is easy to skip: the property's actual electrical load. Skip it and the fix is rarely simple. It is usually a solar system that cannot carry the loads it was meant to, or an automation layer that trips breakers it was never coordinated with.
This guide explains what load planning involves, shows a simple worked example, and covers the power-quality issues that matter in Nigerian buildings.
What load planning actually means
Load planning works out what a property draws, when, and from which circuits, before deciding how much solar, battery storage, backup or automation it needs. It sounds like a formality. In practice it is the difference between a system sized for the property and one sized for a guess.
- A full inventory of major loads: air conditioning, water heating, kitchen equipment, pumps, and any heavy commercial equipment
- Diversity, since not every load runs at full power at once, so systems are sized for the realistic peak rather than the theoretical total
- Circuit-level mapping, showing which loads sit on which distribution board and breaker
- Growth allowance for loads the property does not have yet but is likely to add
Measure, do not guess
Nameplate ratings tell you the maximum an appliance can draw, not what it actually uses. Measurement gives a much truer picture. A clamp meter survey of each circuit, a smart meter on the main supply, or metering switches such as the Sonoff POW Elite on individual heavy loads show real consumption over a normal week, including when the peaks happen.
A simple worked example
Consider a family home that wants solar backup for the evening and night. A load survey might find:
- Lighting, fans, TVs and charging: around 400W when in use